Contract Revenue

Contract Revenue :

Contract revenue should comprise:

(a) the initial amount of revenue agreed in the contract; and

(b) variations in contract work, claims and incentive payments: (

i) to the extent that it is probable that they will result in revenue; and

(ii) they are capable of being reliably measured.

Contract revenue is measured at the consideration received or receivable. The measurement of contract revenue is affected by a variety of uncertainties that depend on the outcome of future events. The estimates often need to be revised as events occur and uncertainties are resolved. Therefore, the amount of contract revenue may increase or decrease from one period to the next. For example:

(a) a contractor and a customer may agree to variations or claims that increase or decrease contract revenue in a period subsequent to that in which the contract was initially agreed;

(b) the amount of revenue agreed in a fixed price contract may increase as a result of cost escalation clauses;

(c) the amount of contract revenue may decrease as a result of penalties arising from delays caused by the contractor in the completion of the contract; or

(d) when a fixed price contract involves a fixed price per unit of output, contract revenue increases as the number of units is increased

A variation is an instruction by the customer for a change in the scope of the work to be performed under the contract. A variation may lead to an increase or a decrease in contract revenue. Examples of variations are changes in the specifications or design of the asset and changes in the duration of the contract. A variation is included in contract revenue when:

(a) it is probable that the customer will approve the variation and the amount of revenue arising from the variation; and

(b) the amount of revenue can be reliably measured.

A claim is an amount that the contractor seeks to collect from the customer or another party as reimbursement for costs not included in the contract price. A claim may arise from, for example, customer caused delays, errors in specifications or design, and disputed variations in contract work. The measurement of the amounts of revenue arising from claims is subject to a high level of uncertainty and often depends on the outcome of negotiations. Therefore, claims are only included in contract revenue when:

(a) negotiations have reached an advanced stage such that it is probable that the customer will accept the claim; and

(b) the amount that it is probable will be accepted by the customer can be measured reliably

Incentive payments are additional amounts payable to the contractor if specified performance standards are met or exceeded. For example, a contract may allow for an incentive payment to the contractor for early completion of the contract. Incentive payments are included in contract revenue when:

(a) the contract is sufficiently advanced that it is probable that the specified performance standards will be met or exceeded; and

(b) the amount of the incentive payment can be measured reliably.